Construction calculation report
Construction Cost Estimate
Kolkata · Area → cost
Inputs
- Mode
- forward
- Location
- Kolkata
- Property type
- independent_house
- Built-up area
- 1,500 sq ft
- Floors
- 2
- Quality
- standard
- Contingency
- 10%
Result
- Estimated total
- ₹29,33,700
- Cost per sq ft
- ₹1,778
- Likely range
- ₹25,81,656 – ₹32,85,744
- Materials (est.)
- ₹13,86,840
- Labour (est.)
- ₹8,53,440
- Confidence
- medium (80%)
Breakdown
- Cement
- ₹2,13,360 (7.3%)
- Steel
- ₹3,20,040 (10.9%)
- Sand
- ₹1,33,350 (4.5%)
- Aggregate
- ₹1,33,350 (4.5%)
- Bricks / blocks
- ₹1,86,690 (6.4%)
- Flooring
- ₹2,13,360 (7.3%)
- Paint
- ₹1,06,680 (3.6%)
- Electrical
- ₹1,60,020 (5.5%)
- Plumbing
- ₹1,33,350 (4.5%)
- Doors / windows
- ₹1,60,020 (5.5%)
- Labour
- ₹5,86,740 (20%)
- Professional fees
- ₹1,06,680 (3.6%)
- Other
- ₹2,13,360 (7.3%)
- Contingency
- ₹2,66,700 (9.1%)
Assumptions
- Base rate ₹1800/sqft (national indicative) for Kolkata.
- Quality multiplier ×1 (standard) maps to STANDARD specifications for detailed BOQ — the ₹/sq ft total remains a quick estimate.
- Floor multiplier ×1.04 for 2 floor(s).
- Location multiplier ×0.95.
- Cost split material 52% / labour 32% / misc 16%.
- Market rates in model: steel ₹55/kg, cement ₹380/bag, labour index 100.
- Contingency 10% on subtotal.
- Category and phase shares are planning allocations, not contractor bills.
- Always verify rates with local contractors and suppliers before budgeting.
- Verify locally with suppliers or contractors before budgeting. These are not live market prices.
Methodology
total ≈ (area_sqft × cost_per_sqft + features) × (1 + contingency%)
- Start from base location rate (₹1800/sqft) for Kolkata.
- Apply quality multiplier (standard: ×1) and attach STANDARD specification mapping (not a substitute for a detailed BOQ).
- Apply floor multiplier (×1.04).
- Foundation type left at default (×1.0).
- Structure type left at default (×1.0).
- Add optional features (0 item(s), ₹0).
- Split into material / labour / miscellaneous using configured percentages.
- Adjust for steel / cement / labour rate overrides vs market defaults when provided.
- Add contingency (10%).
- Publish a likely range of ±12% around the mid estimate.